Images of construction progress of Nhi Thanh Water plant - BIWASE Long An

07 01-2025

CONSTRUCTION IMAGE REPORT

PROJECT: NHI THANH WATER PLANT – PHASE 3: INVESTMENT TO INCREASE CAPACITY TO 120,000M³/DAY

(From October 25, 2024, to January 7, 2025)

• Construction volume and progress report 

+ Construction of the D1200mm raw water pipeline along DT818 Road: Completion of pipe installation and asphalt resurfacing of the entire road surface. Overall progress: 100% complete.

+ Construction of the D1200mm raw water pipeline from Overpass No. 7 to Overpass No. 3: 7128m: Not finished.

+ Construction of the D1200mm clean water pipeline along National Highway 1A: 3.222/6.800m. Overall progress reaches 47%.

+ Nhi Thanh Water plant construction: 

Pile driving: 947/973 piles: 97% complete

Structural works: Concrete pouring for the bottom slabs and walls of filter tank 1, filter tank 2, reaction tank, and bottom slab of the reservoir. Overall progress for structural works: 30% complete.

1. Nhi Thanh Water plant construction

(Installation of steel reinforcement, formwork for the bottom slab, and walls of treatment units)

(Concrete pouring for the bottom slab and walls of treatment units)

(Concrete walls of the filter tank and the reservoir)

(Completion of the chlorine house)

(Contruction of the bottom of the reservoir)

(Overall construction)

2. Construction of the D1200 raw water pipeline along DT 818 Road, Nhi Thanh Commune, Thu Thua District.

(Asphalt resurfacing for trench restoration)

(Drilling to inspect the thickness of the asphalt resurfacing)

(The surface of DT 818 Road after construction completion)

3. Construction of the D1200 clean water pipeline along National Highway 1A

(Construction of trench excavation with Cajuput pile)

(Installation of concrete supports for the pipeline)

(Installation of DN 1200mm castiron pipeline)

(Installation of fences, traffic safety signs, and traffic regulation measures)